Construction Updates

Ronald Read Pavilion Construction Updates

Updates for the project will be published here.

To view the full Boiler Project Schedule, click here.

Friday, September 21 – Two of the four new boilers will be delivered on 9/21.  This is expected to take about 4 hours from the time the boilers arrive until the time they are inside of the building.  This delivery will occur during regular business hours.

Wednesday, November 14 or Thursday, November 15 – A contractor for BMH will be cutting the exterior brickwork on the boiler building.  This to create space for the ventilation louvers to be installed per the plans provided in the ACT 250 permit application.